During construction, the Ministry of Transportation and Infrastructure is committed to minimize delays and maximize predictability for all commuters (drivers, transit users, cyclists and pedestrians) by undertaking the majority of work outside of peak traffic periods.  The ministry will not allow lane closures for construction on Sundays, statutory holidays, or during the hours of 5:30 a.m. to 8:00 p.m. Monday through Saturday.  Nighttime work may include 15-30 minute traffic stoppages and advance notice will be provided. The contractor may work throughout the night for some activities, but every effort will be made to keep noise minimal for nearby residents. Ministry staff are monitoring traffic throughout to ensure any delays related to construction are minimal.

Regular updates and advance notification will be provided as needed through DriveBC, social media, traffic advisories, and changeable message signs.

August 12, 2019

CONSTRUCTION on Galloping Goose Regional Trail

Recreational cyclists, bike commuters and pedestrians who use the Galloping Goose Trail are advised that intermittent overnight trail closures may be in effect at the McKenzie interchange construction site from August 13th through November 5th. No trail closures will happen during peak usage periods or on Sundays or holidays. If closures are necessary, they will only occur between 8:30 p.m. and 5:30 a.m. During closures, trail users can detour onto Burnside Road between Belgrave Road and the Burnside bridge. More information at https://news.gov.bc.ca/releases/2019TRAN0139-001588

May 14, 2019

The second and final construction contract for the McKenzie interchange project is 50% complete, with current work focusing on building the overpass that will allow Highway 1 traffic to travel through the intersection without stopping.

The Ministry of Transportation and Infrastructure anticipates removing the traffic lights on Highway 1 by this upcoming winter. The entire project, including the loop ramp, landscaping and transit facilities, is now expected to finish by summer 2020.

October 31, 2018

Beginning in November, 2018, southbound highway traffic entering the intersection will be shifted to new temporary Admirals Road on- and off-ramps.

The traffic shift marks a major milestone for the McKenzie interchange project, designed to improve the “Colwood Crawl” and ease South Island traffic congestion.

These ramps will allow crews to lower Highway 1 and build the eventual overpass across the highway connecting McKenzie Avenue and Admirals Road.

This new southbound configuration, along with the existing northbound traffic pattern, will be in place until the interchange opens to free-flowing traffic by late summer 2019. The entire interchange project is anticipated to cut roughly 20 minutes off peak commute times and is on schedule to wrap up by the end of 2019.

 

Visualization of new traffic pattern at Highway 1 and McKenzie Avenue

McKenzie Interchange Map- November 2018 (click to enlarge)

 

Blasting activity continues – July 2018

On June 11, 2018, drilling and blasting work adjacent to the current highway alignment resumed. The updated construction schedule will see this work continuing into early August.

  • Drilling activities are permitted between 3:00pm & 9:00pm Monday to Friday and 9:00am & 9:00pm Saturdays.
  • Blasting is permitted between 8:00pm & 10:00pm Monday to Saturday. Preparatory work for blasting will be completed throughout the day with possible multiple blasts during the permitted evening time window.
  • No blasting permitted on Sundays or Statutory Holidays

For safety, please obey traffic control personnel.

Warning signs will be as follows:

  • Twelve (12) short whistles, followed by a brief pause;
    • Blast(s) will be detonated;
    • A long whistle indicates all is clear.

 

New Traffic Pattern at Highway 1 and McKenzie Avenue – May 2018

On June 11th, the northbound lanes on Highway 1 began detouring onto the newly constructed ramps for the future interchange. This new location for northbound highway traffic will be in place until construction of the overpass crossing Highway 1 is completed in summer 2019.

Progress has been made on widening the Galloping Goose Trail and constructing crossings over both McKenzie Avenue and Highway 1, to keep pedestrians and cyclists safer by being separated from vehicle traffic. Pedestrians are now able to use the trail infrastructure to cross Highway 1 and McKenzie Avenue instead of waiting at the Highway 1/McKenzie traffic signal.

While the intersection configuration will be changed, the Ministry of Transportation and Infrastructure expects vehicle traffic to continue to flow at the existing speeds and there will be no changes to the signal timing operations.  The ministry asks drivers to follow signs, watch for workers, and keep moving through the construction site while obeying the construction speed limit of 60 km/h.

The southbound traffic on Highway 1 is expected to be detoured on a new alignment later this summer as construction progresses. These lane shifts will allow crews to excavate the existing highway down and construct the overpass across the highway.

Visualization of new traffic pattern at highway 1 and McKenzie Avenue (May 2018)

McKenzie Interchange Map – May 2018 (click to enlarge)

 

Six Month Look Ahead

 

Current Traffic Advisories

For the most up-to-date travel information and all traffic advisories, please check DriveBC.

The following is an aggregate of DriveBC traffic advisories for the construction area:

CONSTRUCTION on Highway 1 at Exit 6: McKenzie Ave

Highway 1 (on Vancouver Island), in both directions. Road construction work at Exit 6: McKenzie Ave (Saanich). 900m north to 800m south of McKenzie. Possible delays between 8pm-530 am nightly until further notice. 60 km/hr construction speed zone in effect 24/7. Traffic pattern changes on McKenzie Ave & Admirals Road ongoing until Oct 15 for construction of the Hwy 1 underpass approaches. Last updated Wed Aug 14 at 3:57 PM PDT. (DBC-2630)

CONSTRUCTION on Highway 1 Tillicum Rd

Highway 1 (on Vancouver Island), southbound. Road construction work between Tillicum Rd and Carey Rd for 1.1 km (Saanich). Until Mon Sep 30. From 7:00 PM to 5:30 AM PDT daily. Southbound lane closure. Lane Shift SB slow/fast lanes between Tillicum Road and Carey Road, median barrier removed. 24hrs a day July through September 2019. Last updated Wed Jul 3 at 3:14 PM PDT. (DBC-9804)

CONSTRUCTION on Highway 17 Vernon Crt

Highway 17. Electrical maintenance planned between Vernon Crt and Ravine Way for 0.3 km (Saanich). Starting Sun Sep 29 at 9:00 PM PDT until Mon Sep 30 at 5:00 AM PDT. Last updated Thu Aug 29 at 12:50 PM PDT. (DBC-11409)

 

View Previous Advisories